Andrew Kerr Aged Care


PROJECT NAME: Andrew Kerr Aged Care – Mornington

SECTOR: Aged Care

BUILDER / CLIENT: FourSQ

PROJECT MANAGER: Jarryd Bailey

INSTALLATION CONTRACTORS: Cameron Bailey

COMMENTS:

Cotter Floors competitively tendered the Andrew Kerr Aged care project and successfully negotiated the floorcoverings contract with FourSQ construction.

The project which consisted of existing and new build structures was staged over approximately 4 months. The scope included 62 bedrooms with ensuites and all other general areas such as corridors, meals areas, amenities, etc both in hard and soft finishes.

Cotter Floors also carried out all relevant preparation, including diamond grinding, moisture protection, cementitious screeds, masonite hardboard, and fiber cement sheet underlays to satisfactorily receive the below-mentioned materials. Overall the project was a great success for Cotter Floors, the extended Foursq team, and most importantly the client.

MATERIALS:

1,275m2 Armstrong – Timberline “Calde 4X031303”

315m2 / 495lm coving Armstrong – Accolade Foothold “Spice White 5A523561”

185m2 / 200lm coving Armstrong – Accolade Foothold “Whitehaven 5A503771”

32m2 / 58lm coving Armstrong – Accolade Foothold “Sand Grey 5A523151”

2300m2 Interface – Near and Far “Driftwood NF 401 7959-005-000

6blm Godfrey Hirst – Concourse “Steel 7400”

7 x Birrus – Prefab 10mm Ultramats “Café Noir”

SHARE THIS PROJECT!

Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn
Share on google
Google+

PROJECT SCOPE DRAWINGS:

PROJECT SUPPLIERS:

Providing Victorias Flooring Solutions Since 1955!

Tel: 03 8795 7835
admin@cotterfloors.com.au
15/25 Conquest Way Hallam, VIC 3803